Part 2 · 2024 — 2026
Accumulated data becomes process
BIM quantities, once a verification tool on individual sites, became the company's cost management system.
Over the eight years of Part 1, structural frame BIM data generated on every project piled up at Contractor K. Once that accumulation passed a critical point, things that had been impossible became possible.
From here the goal changes. Part 1 asked “are the quantities right?”; Part 2 asks “how do we control cost-ratio risk?” These were the goals Contractor K set, stage by stage.
Goals by stage — what was to be gained from order intake to settlement
BIM-data-driven bid review → support across the whole execution process
Build a transparent, BIM-data-driven quantity management system from order intake to settlement
Order intake
Accurate quantity take-off
- · Eliminate risk of omissions
- · Prevent over- and under-counting
- · Improve cost accuracy
- · Secure bid competitiveness
Execution
BIM data integration
- · Manage quantity variation
- · Make increases visible
- · Monitor actual placement
- · Data-driven control
Settlement
Transparent settlement
- · BIM-based decisions
- · Transparent subcontractor settlement
- · Evidence for contract increases
- · Minimize cost-ratio risk
Accurate forecasting → change management → transparent settlement, to minimize cost-ratio risk
2.1The workflow changed
The Part 1 process worked on a single site. Today it spans the whole project lifecycle. Same company, same tool — but the point at which it is used is completely different.
Current workflow — one full turn of the frame quantity
Bid · order intake
Frame BIM quantity take-off
General building — BIM modeling
Housing sites — estimated from the accumulated BIM DB
PRE-CON
Preliminary execution quantity
Construction plan reflected and reviewed
Cost risk stripped out before groundbreaking
Frame construction
BIM for final execution
Quantities updated for design changes and site requests
Rebar cost monitoring · continuous
Ordered vs. delivered reconciled
Settlement
Review of settlement documents
Overruns against execution quantity identified
Evidence against over-claimed progress billing
Completion
Captured into the BIM DB
Organized by member type
Becomes the estimating basis for the next project
Each turn makes the next turn more accurate — that cycle is the heart of Part 2.
In the early phase this flow existed only after groundbreaking, and the data stopped when the project ended.
2.2Who does it — what to keep and what to hand over
You might expect a company with eight years behind it to do everything itself. The opposite is true. Contractor K hands much of the hands-on quantity take-off to specialist service firms. What it keeps is not the work — it is the standards and the judgement.
Who does what by stage — kept in-house vs. handed over
In-house
Conceptual estimate · technical proposal
Bid quantity down 2–3%
Model · quantity review
Database & standards
↕ Deliverables reviewed in-house
Specialist service firm
Conceptual estimate from BIM DB
Preliminary execution take-off
Frame BIM modeling
Final execution take-off
Rebar shop drawings
What is held in-house is deciding “what is correct” — the making is handed over.
Frame BIM modeling and quantity take-off are done by specialist firms; in-house sets the standards and verifies the results.
2.3Estimating quantities without a model
The most dramatic change came at the order intake stage. Once members from past projects were captured in a database by type, quantities for a new project could be estimated before the detailed drawings even existed.
- Past projects captured in a database by member type — transfer columns · unit slabs · isolated footings · core walls · party walls
- New sites only need a MASS model for conceptual estimating, mapped to rebar quantities from the member database
- Not 1:1 but many:1 matching — accuracy secured by a classification system based on design conditions (floor count, wind exposure, structural scheme)
Better quantity accuracy at the bid stage translates directly into competitiveness, because you no longer have to add contingency you cannot justify.
2.4How close did BIM quantities come to 2D estimating?
Verified against the accumulated data, BIM net quantities reached the following levels versus conventional 2D estimating.
BIM net quantity vs. 2D estimating(2D estimate = 100)
Concrete
97%
3% below the 2D estimate — the customary contingency
Rebar
96%
4% below the 2D estimate
↑ 2D estimate 100%
2.5In real time, not at settlement
Conventional cost management happened at points in time — interim and final settlement. By the time a problem showed up, it was often past the point of no return.
The shift in cost management(conceptual)
AS-IS · stage-gate control
By the time you see the problem, it is hard to recover
TO-BE · real-time trend control
Any drift shows immediately, so the target holds
What supports this shift in practice is rebar cost monitoring. Begun in Part 1 as a monthly report, it settled into a continuous management system as the data accumulated. What it manages — duplicate ordering across zones, excess contingency rebar, excess temporary fixing bars — is exactly the territory that, in Part 1, “had no standard and so was up for negotiation”.
Crucially, this only works on top of a trustworthy baseline — the BuilderHub quantity. If you cannot trust the quantity you are comparing against, reconciling it more often means nothing.
2.6Results
Results across four sites. These are completion-basis projections, and publicly announced figures.
Savings at completion
approx. 1,300tons
vs. planned quantity
Reduction rate
approx. 5%
four sites combined
In monetary terms
approx. KRW 1.8billion
completion-basis projection
| Site | Planned qty (tons) | Delivered per shop drawing (tons) | Reduction |
|---|---|---|---|
| Site A | approx. 5,350 | approx. 5,230 | approx. 2% |
| Site B | approx. 10,700 | approx. 10,000 | approx. 6% |
| Site C | approx. 4,730 | approx. 4,540 | approx. 4% |
| Site D | approx. 6,200 | approx. 5,860 | approx. 6% |
| Total | approx. 27,000 | approx. 25,600 | approx. 5% |
A secondary but substantial practical benefit was less time spent analysing settlement causes and preparing paperwork. With the evidence held as data, fewer people were needed to explain the differences.
The customer and project names are anonymized, and figures are cited only from publicly announced material and within a pre-agreed scope. Diagrams and charts were newly produced from the source data.
