Part 1 · 2017 — 2023
Making invisible quantities visible
Why were rebar quantities always off, and why could no one explain it?
1.1Formulas gave no evidence
The problem with the old method was not accuracy — it was traceability. When quantities came out higher than planned, there was no way to tell whether the increase was legitimate or over-calculated. Every number existed only as the output of a formula.
- The continuity of the building is not reflected — calculating member by member makes connections and anchorages diverge from reality.
- Contingency is added by convention — how much was added, and why, is buried inside the formula.
- Quantity can be hidden in the drawings — reviewing drawings by eye rarely finds it.
1.2Someone benefits when the quantity grows
The deeper problem is that the incentives run in opposite directions. Rebar quantities are fixed as they pass from head office to the site, to the rebar shop drawing firm, to the fabrication yard — and along that chain, more quantity means more money for someone.
How rebar quantity gets fixed — and where the incentives collide
The same quantity, incentives pointing opposite ways
Head office
Sets execution budget
Site
Decides placement rules
Rebar shop drawing firm
Prepares bar schedule
Fabrication yard
Fabricates and delivers
Rebar tons ↑ → margin ↓
Buyer side — more quantity means higher cost
Rebar tons ↑ → revenue ↑
Supply side — more quantity means more sales
1.3Putting three numbers side by side
Contractor K's approach was simple: produce three quantities for the same building and compare them — then chase down the “why” behind every difference.
Three-way comparison — from plan to actual placement
STEP 1 · Execution budget stage
Conventional 2D formula estimate
Drawings + Excel formulas + customary contingency
BuilderHub quantity
Taken from the 3D model · calculation basis included
1st comparison — is the execution quantity sound?
Design changes · site requests → model regenerated
Baseline quantity reflecting actual pre-construction conditions
STEP 2 · Actual placement verification
BuilderHub recalculated quantity
Latest model with all changes reflected
Actual rebar shop drawing quantity
Fabricated quantity actually placed on site
2nd comparison — what causes the gap?
1.4Where it is used — the workflow in the early adoption phase
“Where do we slot BuilderHub in?” is the first question every new customer asks. Here is the actual flow at the pilot site in the first year.
Early adoption workflow — pilot site
① BIM modeling · in-house
- · Supported by one head office BIM specialist
- · About 5 months to modeling
- · Done by site staff, not outsourced
② Using the BIM model
Site BIM training → model in use
Constructability review · quantity review by work package
③ Analysing results
Analysis of BIM outcomes
Fed into the next site
BuilderHub enters at two points — creating the structural frame 3D BIM, and the quantities taken from that model
Everything else stays as it was. You are not building a new process; you start by changing two points in the existing flow.
In the first year this was enough. No database, no conceptual estimating, no continuous monitoring yet.
1.5Rebar is not one thing
The most important fact the repeated comparisons revealed was that rebar splits into two categories. This distinction is not well known outside Korea, but a large share of the quantity gap originates here.
Structural rebar and assembly rebar
Structural rebar
Determined by structural calculation · shown on structural drawings
92~95%
5~8%
Structural rebar · 26 types
Main bars · reinforcing bars · vertical bars · horizontal bars · stirrups · U-bars ···
Set by structural calculation, so the standard is clear and it can be verified
Assembly rebar · 15 types
Chairs · purlin bars · dowels · spacing bars · auxiliary stirrups ···
Relies on subcontractor experience — there was no standard
5–8% sounds small, but on a site with several thousand tons of rebar it is hundreds of tons. And no standard means it becomes a matter of negotiation.
1.6Why the gap appears — cost monitoring
Comparing model quantities against rebar shop drawing quantities is not enough. Control only begins when you can name the cause of a difference. So a rebar cost monitoring report — reconciling rebar ordered after groundbreaking against the 3D BIM model — was issued monthly.
- Overall and per-building comparison tables of BIM quantities against the estimate
- Ordered-quantity comparison charts and tables against BIM quantities
- Comparative analysis tables by total / building / floor
- Detailed analysis of the major differences
Repeating this work, the causes of the differences resolved into four categories.
| Cause of difference | Nature |
|---|---|
| Change in design documents | Unpredictable — handled by updating the model |
| Site detail changes for constructability lap length adjustments · purlin bars · long site bars | Legitimate difference — absorbed into the standard |
| Items not decided or not modeled in advance sleeves · sumps · MEP boxes, etc. | A scope issue — stated in the take-off rules |
| Modeler error | A quality issue — solved by standards and training |
What matters is that quantity remains that fits none of the four. In the review results these are classified as “unexplained quantity present in the rebar shop drawing”. Under the old method such quantity existed but never surfaced — there was no baseline to compare against.
1.7Building the standard
Contractor K established company-wide shop drawing guidelines for assembly rebar — putting numeric standards on items that had been settled by convention.
| Item | Before (convention) | After (standard) |
|---|---|---|
| Support bar spacing, foundation top bars | @ 1,000 ~ 1,200 | @ 1,500 |
| Wall connection bars | 8-HD10 | 4-HD10 |
| Wall–foundation connection bars | Minimization rule applied | — |
At the same time, the shop drawing stage was made to review over-reinforcement and shop drawing omissions together. Once the standard existed, training and consultation with subcontractors followed, so that it actually worked on site.
1.8At first they did it themselves
In the first year, Contractor K did the BIM modeling with site staff, without any outsourced service.
“So that our own site staff can operate BIM data themselves”
— the goal at the start
BIM training was run for site CAD staff, BIM was built into the new-hire curriculum, and videos and user manuals were produced and distributed internally.
But this did not mean they intended to keep modeling in-house forever. The aim was to have the eye to judge. Why did the quantity come out this way, which standard should apply, is the deliverable correct — if you cannot judge that yourself, nothing you hand out gets verified.
And once they had confirmed how the process should run, they moved to outsourcing. Today a specialist firm models for four weeks, and the in-house BIM group and the site review the model and quantities for one week before feeding them into the final execution budget.
The order matters: build in-house capability → establish the process → move to outsourcing. Reverse it and you receive deliverables you cannot verify. Outsourcing works only once you have a standard for what to ask and how to judge what comes back.

The customer and project names are anonymized, and figures are cited only from publicly announced material and within a pre-agreed scope. Diagrams and charts were newly produced from the source data.